Work begins on next stage of Burrendong Way upgrade

May 14, 2019

Work is under way on Orange’s City Council’s upgrade of a section of Burrendong Way.

A council contractor is re-building a 600 metre long section of Burrendong Way, south from the northern bypass roundabout to Sunrise Way.

The work began this week and is expected to continue until September, weather permitting.

The road building project will include :

  • removing the current road surface
  • replacing the underlying pavement down to depth of between 150 and 300 mm
  • re-surfacing the road with hot-mix bitumen
  • kerb & gutter on the eastern side of the road.

As part of the project, a footpath will be built on the eastern side of the road with connections to walking paths in the nearby wetlands.

The project is part of a long-term plan to upgrade Burrendong Way. Sections of the road north of the roundabout have already been completed.

Traffic control measures will be in place, and at least one lane of the road will be open at all times, however drivers are being urged to use alternative routes to avoid possible delays.

For the next three weeks drivers on the bypass won’t be able to turn south towards Orange, while the first stage of the project gets underway.



Share Work begins on next stage of Burrendong Way upgrade on Facebook Share Work begins on next stage of Burrendong Way upgrade on Twitter Share Work begins on next stage of Burrendong Way upgrade on Linkedin Email Work begins on next stage of Burrendong Way upgrade link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>